Which of the following processes are involved under the COBIT framework?
The correct answer is A. Managing the IT workforce. C. Conducting IT risk assessments. D. Developing a strategic plan. The Control Objectives for Information and related Technology (COBIT) is a set of best practices (framework) for information technology (IT) management, which provides managers, auditors, and IT users with a set of generally accepted measures, indicators, processes and best…
Question
Which of the following processes are involved under the COBIT framework?
Options
- AManaging the IT workforce.
- BCorrecting all risk issues.
- CConducting IT risk assessments.
- DDeveloping a strategic plan.
How the community answered
(21 responses)- A71% (15)
- B29% (6)
Explanation
The Control Objectives for Information and related Technology (COBIT) is a set of best practices (framework) for information technology (IT) management, which provides managers, auditors, and IT users with a set of generally accepted measures, indicators, processes and best practices to assist them in maximizing the benefits derived through the use of information technology and developing appropriate IT governance and control in a company. It has the following 11 processes: Developing a strategic plan. Articulating the information architecture. Finding an optimal stage between the IT and the organization's strategy. Designing the IT function to match the organization's needs. Maximizing the return of the IT investment. Communicating IT policies to the user's community. Managing the IT workforce. Obeying external regulations, laws, and contracts. Conducting IT risk assessments. Maintaining a high-quality systems-development process. Incorporating sound project-management techniques. Answer: B is incorrect. Correcting all risk issues does not come under auditing processes.