nerdexam
GIAC

GSLC · Question #422

You are the program manager for your organization. You have proposed a program that will cost $750,000 and will last for four years. Management is concerned with the cost of the program in relation…

The correct answer is C. $946,857. This question requires calculating the future value of a $750,000 investment at a 6% annual rate of return compounded over four years to determine the minimum acceptable program return.

Metrics, Reporting & Future State

Question

You are the program manager for your organization. You have proposed a program that will cost $750,000 and will last for four years. Management is concerned with the cost of the program in relation to the return your program will bring. If the rate of return is six percent what is the minimum value your project should return in four years based on the investment of the program?

Options

  • A$795,000
  • B$750,001
  • C$946,857
  • D$750,000

How the community answered

(60 responses)
  • A
    7% (4)
  • B
    3% (2)
  • C
    78% (47)
  • D
    12% (7)

Why each option

This question requires calculating the future value of a $750,000 investment at a 6% annual rate of return compounded over four years to determine the minimum acceptable program return.

A$795,000

$795,000 incorrectly applies only a single period of 6% growth ($750,000 x 1.06) rather than compounding the rate over all four years.

B$750,001

$750,001 is barely above the principal and completely ignores the 6% required rate of return compounded over four years.

C$946,857Correct

The future value formula FV = PV x (1 + r)^n yields $750,000 x (1.06)^4 = $750,000 x 1.26248 = $946,857, which is the minimum value the program must return to satisfy a 6% annual rate of return over its four-year lifespan. Any return below this amount means the program fails to meet the required rate of return on the $750,000 investment.

D$750,000

$750,000 is the original investment amount representing a zero return, which does not satisfy any positive rate of return requirement.

Concept tested: Future value calculation for program return on investment

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#ROI calculation#program investment#future value#financial justification

Community Discussion

No community discussion yet for this question.

Full GSLC Practice