GISF · Question #96
You are the project manager of a new project in your organization. You and the project team haveidentified the project risks, completed risk analysis, and are planning the most appropriate…
The correct answer is C. Decision tree analysis. See the full explanation below for the reasoning.
Question
You are the project manager of a new project in your organization. You and the project team haveidentified the project risks, completed risk analysis, and are planning the most appropriate riskresponses. Which of the following tools is most effective to choose the most appropriate riskresponse?
Options
- AProject network diagrams
- BDelphi Technique
- CDecision tree analysis
- DCause-and-effect diagrams
How the community answered
(24 responses)- A4% (1)
- B8% (2)
- C83% (20)
- D4% (1)