You work as a project manager for TYU project. You are planning for risk mitigation. You need toidentify the risks that will need a more in-depth analysis. Which of the following activities will…
The correct answer is B. Qualitative analysis. See the full explanation below for the reasoning.
Question
You work as a project manager for TYU project. You are planning for risk mitigation. You need toidentify the risks that will need a more in-depth analysis. Which of the following activities will helpyou in this?
Options
- AQuantitative analysis
- BQualitative analysis
- CEstimate activity duration
- DRisk identification
How the community answered
(20 responses)- A10% (2)
- B70% (14)
- C15% (3)
- D5% (1)