Which of the following are some of the parts of a project plan? Each correct answer represents a complete solution. Choose all that apply.

The correct answer is A. Risk identification B. Project schedule C. Team members list. See the full explanation below for the reasoning.

Question

Which of the following are some of the parts of a project plan? Each correct answer represents a complete solution. Choose all that apply.

Options

  • ARisk identification
  • BProject schedule
  • CTeam members list
  • DRisk analysis

How the community answered

(56 responses)
  • A
    71% (40)
  • D
    29% (16)