nerdexam
GIAC

GISF · Question #48

You and your project team have identified the project risks and now are analyzing the probability andimpact of the risks. What type of analysis of the risks provides a quick and high-level review of…

The correct answer is C. Qualitative risk analysis. See the full explanation below for the reasoning.

Question

You and your project team have identified the project risks and now are analyzing the probability andimpact of the risks. What type of analysis of the risks provides a quick and high-level review of eachidentified risk event?

Options

  • AA risk probability-impact matrix
  • BQuantitative risk analysis
  • CQualitative risk analysis
  • DSeven risk responses

How the community answered

(46 responses)
  • A
    13% (6)
  • B
    7% (3)
  • C
    78% (36)
  • D
    2% (1)

Community Discussion

No community discussion yet for this question.

Full GISF Practice