nerdexam
GIAC

GISF · Question #383

The executive team wants you to track labor costs for your project as well as progress on task completion and the resulting dates. What information must you update for tasks to provide this…

The correct answer is C. Actual Start, Actual Work, and Remaining Work. See the full explanation below for the reasoning.

Question

The executive team wants you to track labor costs for your project as well as progress on task completion and the resulting dates. What information must you update for tasks to provide this information?

Options

  • AStart, Work, and Remaining Work
  • BActual Start and Percent Complete
  • CActual Start, Actual Work, and Remaining Work
  • DActual Start, Percent Complete, and Remaining Duration

How the community answered

(37 responses)
  • A
    3% (1)
  • B
    14% (5)
  • C
    76% (28)
  • D
    8% (3)

Community Discussion

No community discussion yet for this question.

Full GISF Practice