The executive team wants you to track labor costs for your project as well as progress on task completion and the resulting dates. What information must you update for tasks to provide this information?
Options
- AStart, Work, and Remaining Work
- BActual Start and Percent Complete
- CActual Start, Actual Work, and Remaining Work
- DActual Start, Percent Complete, and Remaining Duration