Which of the following processes is responsible for low risk, frequently occurring low cost changes?
The correct answer is C. Request Fulfillment. See the full explanation below for the reasoning.
Question
Which of the following processes is responsible for low risk, frequently occurring low cost changes?
Options
- AIncident Management
- BIT Facilities Management
- CRequest Fulfillment
- DRelease Management
How the community answered
(19 responses)- A16% (3)
- B5% (1)
- C74% (14)
- D5% (1)