You and your project team want to perform some qualitative analysis on the risks you have identified and documented in Project Web Access for your project. You would like to create a table that…
The correct answer is B. Risk Probability and Impact Matrix. See the full explanation below for the reasoning.
Question
You and your project team want to perform some qualitative analysis on the risks you have identified and documented in Project Web Access for your project. You would like to create a table that captures the likelihood and affect of the risk on the project. What type of a chart or table would you like to create for the project risks?
Options
- ARisk Breakdown Structure
- BRisk Probability and Impact Matrix
- CRisk Review Table
- DRisk Impact and Affect Matrix
How the community answered
(29 responses)- A3% (1)
- B83% (24)
- C10% (3)
- D3% (1)