GIAC
GISF · Question #346
Donna is the project manager for her organization. She is preparing a plan to manage changes to the project should changes be requested. Her change management plan defines the process for…
The correct answer is A. Project Management Information System. See the full explanation below for the reasoning.
Question
Donna is the project manager for her organization. She is preparing a plan to manage changes to the project should changes be requested. Her change management plan defines the process for documenting, tracking, and determining if the changes should be approved or declined. What system is considered the parent of the change control system documented in Donna's plan?
Options
- AProject Management Information System
- BIntegrated Change Control System
- CChange Control System
- DQuality Management System
How the community answered
(37 responses)- A76% (28)
- B14% (5)
- C8% (3)
- D3% (1)
Community Discussion
No community discussion yet for this question.