The correct answer is B. Communications Management Plan. See the full explanation below for the reasoning.

Question

You work as the project manager for Bluewell Inc. Your project has several risks that will affect several stakeholder requirements. Which project management plan will define who will be available to share information on the project risks?

Options

  • ARisk Management Plan
  • BCommunications Management Plan
  • CStakeholder management strategy
  • DResource Management Plan