Question
You are the project manager of SST project. You are in the process of collecting and distributingperformance information including status report, progress measurements, and forecasts. Which ofthe following process are you performing?
Options
- AReport Performance
- BVerify Scope
- CControl Scope
- DPerform Quality Control