Which of the following is not needed for effective procurement planning?
The correct answer is D. Quality risk analysis. See the full explanation below for the reasoning.
Question
Which of the following is not needed for effective procurement planning?
Options
- AActivity resource management
- BProject schedule
- CCost baseline
- DQuality risk analysis
How the community answered
(50 responses)- A6% (3)
- B2% (1)
- C10% (5)
- D82% (41)