Which of the following is not needed for effective procurement planning?

The correct answer is D. Quality risk analysis. See the full explanation below for the reasoning.

Question

Which of the following is not needed for effective procurement planning?

Options

  • AActivity resource management
  • BProject schedule
  • CCost baseline
  • DQuality risk analysis

How the community answered

(50 responses)
  • A
    6% (3)
  • B
    2% (1)
  • C
    10% (5)
  • D
    82% (41)