Which project management risk event would you be using if you changed the sequence of activities toreduce the probability of the project being delayed?
The correct answer is D. Avoidance. See the full explanation below for the reasoning.
Question
Which project management risk event would you be using if you changed the sequence of activities toreduce the probability of the project being delayed?
Options
- AEnhancing
- BWithdrawal
- CExploiting
- DAvoidance
How the community answered
(55 responses)- A5% (3)
- B11% (6)
- C4% (2)
- D80% (44)