nerdexam
GIAC

GISF · Question #140

Which project management risk event would you be using if you changed the sequence of activities toreduce the probability of the project being delayed?

The correct answer is D. Avoidance. See the full explanation below for the reasoning.

Question

Which project management risk event would you be using if you changed the sequence of activities toreduce the probability of the project being delayed?

Options

  • AEnhancing
  • BWithdrawal
  • CExploiting
  • DAvoidance

How the community answered

(55 responses)
  • A
    5% (3)
  • B
    11% (6)
  • C
    4% (2)
  • D
    80% (44)

Community Discussion

No community discussion yet for this question.

Full GISF Practice