The correct answer is C. Monitor and Control Risks. See the full explanation below for the reasoning.

Question

Which of the following processes is described in the statement below? "It is the process of implementing risk response plans, tracking identified risks, monitoringresidual risk, identifying new risks, and evaluating risk process effectiveness throughout theproject."

Options

  • APerform Quantitative Risk Analysis
  • BPerform Qualitative Risk Analysis
  • CMonitor and Control Risks
  • DIdentify Risks