nerdexam
GIAC

GISF · Question #104

You are working as a project manager in your organization. You are nearing the final stages ofproject execution and looking towards the final risk monitoring and controlling activities. For…

The correct answer is D. Requested changes. See the full explanation below for the reasoning.

Question

You are working as a project manager in your organization. You are nearing the final stages ofproject execution and looking towards the final risk monitoring and controlling activities. For yourproject archives, which one of the following is an output of risk monitoring and control?

Options

  • AQuantitative risk analysis
  • BRisk audits
  • CQualitative risk analysis
  • DRequested changes

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    18% (5)
  • C
    7% (2)
  • D
    71% (20)

Community Discussion

No community discussion yet for this question.

Full GISF Practice