You are working as a project manager in your organization. You are nearing the final stages ofproject execution and looking towards the final risk monitoring and controlling activities. For yourproject archives, which one of the following is an output of risk monitoring and control?

Options

  • AQuantitative risk analysis
  • BRisk audits
  • CQualitative risk analysis
  • DRequested changes