Which of the following is the BEST set of methods one may use to validate a system once operations have been restored during the Recovery phase of Incident Handling?
The correct answer is D. Follow test plans, use baseline documentation, and utilize business unit testing. Documented test plans, baseline performance or behavior, and business unit testing can be used to validate that a system is back online and behaving as it should.
Incident Response & Cyber Kill Chain
Question
Which of the following is the BEST set of methods one may use to validate a system once operations have been restored during the Recovery phase of Incident Handling?
Options
- AEnsure the system boots, verify the applications start, and check network connectivity
- BObtain legal sign-off, validate the system recovery, and obtain incident handler sign-off
- CMonitor syslog activity, create IDS signatures, and review the firewall configuration
- DFollow test plans, use baseline documentation, and utilize business unit testing
How the community answered
(27 responses)- A4% (1)
- B4% (1)
- C15% (4)
- D78% (21)
Explanation
Documented test plans, baseline performance or behavior, and business unit testing can be used to validate that a system is back online and behaving as it should.
Topics
#incident recovery#baseline validation#IR lifecycle#system restoration