An auditor sees EAPOL frames but no DHCP/ARP from the client. What phase is MOST likely underway?
The correct answer is A. 802.1X / key establishment. You've hit your limit · resets 1pm (America/New_York)
Wireless Security Foundations and Reconnaissance
Question
An auditor sees EAPOL frames but no DHCP/ARP from the client. What phase is MOST likely underway?
Options
- A802.1X / key establishment
- BIP addressing
- CApplication negotiation
- DDNS resolution
How the community answered
(25 responses)- A80% (20)
- B4% (1)
- C12% (3)
- D4% (1)
Explanation
You've hit your limit · resets 1pm (America/New_York)