Refer to the exhibit. Which two statements about the output are true? (Choose two.)

The correct answer is B. The latest revision history for the managed FortiGate does match the FortiGate running D. The latest revision history for the managed FortiGate does not match the device-level database. – conf: in sync – This is the sync status which shows that the latest revision history is in sync with Fortigate’s configuration. – There is a new modification on FortiManager device level DB (dev-db: modified) which wasn’t installed to FortiGate (cond: pending)

Device Management

Question

Refer to the exhibit. Which two statements about the output are true? (Choose two.)

Exhibit

FCP_FMG_AD-7.4 question #27 exhibit

Options

  • AConfiguration changes have been installed on FortiGate, which means the FortiGate configuration
  • BThe latest revision history for the managed FortiGate does match the FortiGate running
  • CConfiguration changes directly made on FortiGate have been automatically updated to the
  • DThe latest revision history for the managed FortiGate does not match the device-level database.

How the community answered

(48 responses)
  • A
    15% (7)
  • B
    79% (38)
  • C
    6% (3)

Explanation

– conf: in sync – This is the sync status which shows that the latest revision history is in sync with Fortigate’s configuration. – There is a new modification on FortiManager device level DB (dev-db: modified) which wasn’t installed to FortiGate (cond: pending)

Topics

#revision history#running configuration#device database#configuration sync