FCP_FAZ_AN-7.4 · Question #17
As part of your analysis, you discover that a Medium severity level incident is fully remediated. You change the incident status to Closed: Remediated. Which statement about your update is true?
The correct answer is C. The incident dashboard will be updated. Changing an incident's status to Closed: Remediated means the incident has been resolved and no longer requires active attention. This action inherently impacts the incident dashboard, which tracks key metrics like active incidents, mean time to resolution, and incident status…
Question
As part of your analysis, you discover that a Medium severity level incident is fully remediated. You change the incident status to Closed: Remediated. Which statement about your update is true?
Options
- AThe incident can no longer be deleted.
- BThe corresponding event will be marked as Mitigated.
- CThe incident dashboard will be updated.
- DThe incident severity will be lowered.
How the community answered
(34 responses)- A6% (2)
- B3% (1)
- C76% (26)
- D15% (5)
Explanation
Changing an incident's status to Closed: Remediated means the incident has been resolved and no longer requires active attention. This action inherently impacts the incident dashboard, which tracks key metrics like active incidents, mean time to resolution, and incident status distribution. The dashboard dynamically updates to reflect the current state of all incidents, including those