What stage immediately precedes testing in the waterfall lifecycle?

The correct answer is B. Development. See the full explanation below for the reasoning.

Question

What stage immediately precedes testing in the waterfall lifecycle?

Options

  • ADesign.
  • BDevelopment.
  • CImplementation.
  • DAnalysis.

How the community answered

(19 responses)
  • A
    11% (2)
  • B
    74% (14)
  • C
    5% (1)
  • D
    11% (2)