Linking a piece of delivered software functionality with a requirement is known as which of the following?
The correct answer is D. Requirements traceabiiity. See the full explanation below for the reasoning.
Question
Linking a piece of delivered software functionality with a requirement is known as which of the following?
Options
- ARequirements validation.
- BRequirements verification.
- CRequirements testing.
- DRequirements traceabiiity.
How the community answered
(48 responses)- A4% (2)
- B15% (7)
- C8% (4)
- D73% (35)