Question

Before requirements can actually be approved to be managed, what must be true about the requirements?

Options

  • ARequirements must support the solution scope.
  • BRequirements are governed by the requirements management plan.
  • CRequirements must support the requirements management plan.
  • DRequirements must be approved by the technical review board.