FBA15 · Question #164
FBA15 Question #164: Real Exam Question with Answer & Explanation
The correct answer is A. Requirements must support the solution scope.. See the full explanation below for the reasoning.
Question
Before requirements can actually be approved to be managed, what must be true about the requirements?
Options
- ARequirements must support the solution scope.
- BRequirements are governed by the requirements management plan.
- CRequirements must support the requirements management plan.
- DRequirements must be approved by the technical review board.