BCS-ISEB
FBA15 · Question #158
When are the acceptance criteria for user acceptance testing defined?
The correct answer is B. When the deliverables of the requirements analysis have been agreed. See the full explanation below for the reasoning.
Question
When are the acceptance criteria for user acceptance testing defined?
Options
- AWhen the deliverables of the system design have been agreed.
- BWhen the deliverables of the requirements analysis have been agreed.
- CWhen the software has been completed and has passed system testing.
- DWhen the users have had the opportunity to use the software for a period of time.
How the community answered
(60 responses)- A10% (6)
- B83% (50)
- C5% (3)
- D2% (1)
Community Discussion
No community discussion yet for this question.