The correct answer is B. A systems development lifecycle.. See the full explanation below for the reasoning.
Question
The V model is an example of which of the following?
Options
- AA business analysis process model.
- BA systems development lifecycle.
- CA concerns-based adoption model.
- DA soft systems methodology.