nerdexam
BCS-ISEB

FBA15 · Question #131

FBA15 Question #131: Real Exam Question with Answer & Explanation

The correct answer is A. The IRR of every project is based on it achieving a Net Present Value of zero.. See the full explanation below for the reasoning.

Question

Which of the following statements is TRUE?

Options

  • AThe IRR of every project is based on it achieving a Net Present Value of zero.
  • BIt is preferable for the calculated IRR of a project to be below bank interest rates,
  • CDiscounted cash flows do not usually take into account the time value of money.
  • DWhen comparing two projects, the one with the lower NPV should be preferred.

Community Discussion

No community discussion yet for this question.

Full FBA15 Practice