During which stage of the Business Analysis Process Model would a gap analysis be carried out?
The correct answer is B. Analyse needs. See the full explanation below for the reasoning.
Question
During which stage of the Business Analysis Process Model would a gap analysis be carried out?
Options
- ADefine requirements.
- BAnalyse needs.
- CEvaluate the options.
- DInvestigate situation.
How the community answered
(24 responses)- A4% (1)
- B83% (20)
- C4% (1)
- D8% (2)