Which of the following is NOT part of a Green IT Procurement process?

The correct answer is C. Negotiating discounts for products with high energy consumption. See the full explanation below for the reasoning.

Question

Which of the following is NOT part of a Green IT Procurement process?

Options

  • ARequiring that suppliers have an effective Health & Safety policy.
  • BEstablishing an up-to-date Supplier and Contracts database.
  • CNegotiating discounts for products with high energy consumption.
  • DImplementing effective escrow agreements for software products.

How the community answered

(20 responses)
  • A
    5% (1)
  • C
    85% (17)
  • D
    10% (2)