nerdexam
EXIN

EX0-118 · Question #115

How can you ensure all stakeholders are informed about the process of your Green IT programme?

The correct answer is B. Create a Communications Plan. See the full explanation below for the reasoning.

Question

How can you ensure all stakeholders are informed about the process of your Green IT programme?

Options

  • ADevelop a Programme Plan.
  • BCreate a Communications Plan.
  • CProduce a Stakeholder Competency Assessment.
  • DMaintain a Stakeholder Map.

How the community answered

(26 responses)
  • A
    4% (1)
  • B
    77% (20)
  • C
    4% (1)
  • D
    15% (4)

Community Discussion

No community discussion yet for this question.

Full EX0-118 Practice