Which of these should a change model include? 1. The steps that should be taken to handle the change 2. Responsibilities; who should do what, including escalation 3. Timescales and thresholds for…

The correct answer is A. 1, 2 and 3 only. See the full explanation below for the reasoning.

Question

Which of these should a change model include? 1. The steps that should be taken to handle the change 2. Responsibilities; who should do what, including escalation 3. Timescales and thresholds for completion of the actions 4. Complaints procedures

Options

  • A1, 2 and 3 only
  • BAll of the above
  • C1 and 3 only
  • D2 and 4 only

How the community answered

(34 responses)
  • A
    74% (25)
  • B
    9% (3)
  • C
    3% (1)
  • D
    15% (5)