EX0-117 · Question #369

EX0-117 Question #369: Real Exam Question with Answer & Explanation

The correct answer is C. All of the above. See the full explanation below for the reasoning.

Question

The Supplier Management process includes: (1) Service Design activities, to ensure that contracts will be able to support the service requirements (2) Service Operation activities, to monitor and report supplier achievements (3) Continual Improvement activities, to ensure that suppliers continue to meet or exceed the needs of the business

Options

  • A1 and 2 only
  • B1 only
  • CAll of the above
  • D1 and 3 only