There are two parties in the V model: EXIN EX0-113 Exam - the supplying party - the accepting party Which system development phase or test phase is not performed by the supplying party?
The correct answer is D. Technical design. See the full explanation below for the reasoning.
Question
There are two parties in the V model:
EXIN EX0-113 Exam
- the supplying party
- the accepting party
Which system development phase or test phase is not performed by the supplying party?
Options
- AFunctional design
- BRealization
- CSystem test
- DTechnical design
How the community answered
(62 responses)- A3% (2)
- B8% (5)
- C5% (3)