During which TMap phase is testing 'dynamic implicit'?

The correct answer is B. Execution. See the full explanation below for the reasoning.

Question

During which TMap phase is testing 'dynamic implicit'?

Options

  • ASpecification
  • BExecution
  • CPreparation

How the community answered

(46 responses)
  • A
    7% (3)
  • B
    78% (36)
  • C
    15% (7)