For a Sprint, progress is monitored in a burn-up chart with bars. What makes the bar become longer?

The correct answer is C. Work is deleted from the Sprint Backlog. In a Sprint burn-up chart, the bar tracks completed work - it grows longer as items are finished and removed from the Sprint Backlog, which is what "deleted" means here: work that has met the Definition of Done and is no longer outstanding. Option A is incorrect because time…

Scrum Artifacts

Question

For a Sprint, progress is monitored in a burn-up chart with bars. What makes the bar become longer?

Options

  • AThe progression of time.
  • BWork is added to the Sprint Backlog.
  • CWork is deleted from the Sprint Backlog.

How the community answered

(69 responses)
  • A
    7% (5)
  • B
    3% (2)
  • C
    90% (62)

Explanation

In a Sprint burn-up chart, the bar tracks completed work - it grows longer as items are finished and removed from the Sprint Backlog, which is what "deleted" means here: work that has met the Definition of Done and is no longer outstanding. Option A is incorrect because time advancing is represented on the chart's horizontal axis, not by bar length - the passage of time alone completes nothing. Option B is incorrect because adding work to the Sprint Backlog increases total scope, which would make the bar harder to fill, not longer. A helpful memory tip: think "burn-up" - the bar climbs up as work is done and dropped off the backlog; more completed = longer bar, not more added.

Topics

#burn-up chart#Sprint Backlog#progress monitoring#visualization