When is it confirmed if a project's objectives have been achieved?
The correct answer is A. During the Closing a Project process. See the full explanation below for the reasoning.
Question
When is it confirmed if a project's objectives have been achieved?
Options
- ADuring the Closing a Project process
- BDuring the final end stage assessment
- CDuring the Controlling a Stage process
- DDuring the Managing Product Delivery process
How the community answered
(49 responses)- A82% (40)
- B2% (1)
- C6% (3)
- D10% (5)