EX0-001 · Question #151
Which of the following availability management activities is/are considered to be proactive as opposed to reactive? (1) Monitoring system availability (2) Designing availability into a proposed…
The correct answer is D. 2 only. See the full explanation below for the reasoning.
Question
Which of the following availability management activities is/are considered to be proactive as opposed to reactive? (1) Monitoring system availability (2) Designing availability into a proposed solution
Options
- ANone of the above
- BBoth of the above
- C1 only
- D2 only
How the community answered
(25 responses)- A4% (1)
- B12% (3)
- C4% (1)
- D80% (20)