EX0-001 · Question #116

Which of these should a change model include? (1) The steps that should be taken to handle the change (2) Responsibilities; who should do what, including escalation (3) Timescales and thresholds for…

The correct answer is A. 1, 2 and 3 only. See the full explanation below for the reasoning.

Question

Which of these should a change model include? (1) The steps that should be taken to handle the change (2) Responsibilities; who should do what, including escalation (3) Timescales and thresholds for completion of the actions (4) Complaints procedures

Options

  • A1, 2 and 3 only
  • BAll of the above
  • C1 and 3 only
  • D2 and 4 only

How the community answered

(22 responses)
  • A
    77% (17)
  • B
    14% (3)
  • C
    5% (1)
  • D
    5% (1)