Which of these should a change model include? (1) The steps that should be taken to handle the change (2) Responsibilities; who should do what, including escalation (3) Timescales and thresholds for…
The correct answer is A. 1, 2 and 3 only. See the full explanation below for the reasoning.
Question
Which of these should a change model include? (1) The steps that should be taken to handle the change (2) Responsibilities; who should do what, including escalation (3) Timescales and thresholds for completion of the actions (4) Complaints procedures
Options
- A1, 2 and 3 only
- BAll of the above
- C1 and 3 only
- D2 and 4 only
How the community answered
(22 responses)- A77% (17)
- B14% (3)
- C5% (1)
- D5% (1)