ECBA · Question #97
ECBA Question #97: Real Exam Question with Answer & Explanation
The correct answer is C. Risk. Risk: the chance that the requirement cannot deliver the potential value, or cannot be met at all. This may include many factors such as the difficulty of implementing a requirement, or the chance that stakeholders will not accept a solution component.
Question
In prioritizing requirements, which of the following factors include difficulty of implementing a requirement, or the likelihood that a requirement cannot deliver its potential value?
Options
- APenalty
- BCost
- CRisk
- DDependency
Explanation
Risk: the chance that the requirement cannot deliver the potential value, or cannot be met at all. This may include many factors such as the difficulty of implementing a requirement, or the chance that stakeholders will not accept a solution component.