In prioritizing requirements, which of the following factors include difficulty of implementing a requirement, or the likelihood that a requirement cannot deliver its potential value?

The correct answer is C. Risk. Risk: the chance that the requirement cannot deliver the potential value, or cannot be met at all. This may include many factors such as the difficulty of implementing a requirement, or the chance that stakeholders will not accept a solution component.

Requirements Life Cycle Management

Question

In prioritizing requirements, which of the following factors include difficulty of implementing a requirement, or the likelihood that a requirement cannot deliver its potential value?

Options

  • APenalty
  • BCost
  • CRisk
  • DDependency

How the community answered

(62 responses)
  • A
    5% (3)
  • B
    2% (1)
  • C
    92% (57)
  • D
    2% (1)

Explanation

Risk: the chance that the requirement cannot deliver the potential value, or cannot be met at all. This may include many factors such as the difficulty of implementing a requirement, or the chance that stakeholders will not accept a solution component.

Topics

#requirements prioritization#risk factors#prioritization criteria#implementation difficulty