ECBA · Question #97
In prioritizing requirements, which of the following factors include difficulty of implementing a requirement, or the likelihood that a requirement cannot deliver its potential value?
The correct answer is C. Risk. Risk: the chance that the requirement cannot deliver the potential value, or cannot be met at all. This may include many factors such as the difficulty of implementing a requirement, or the chance that stakeholders will not accept a solution component.
Question
In prioritizing requirements, which of the following factors include difficulty of implementing a requirement, or the likelihood that a requirement cannot deliver its potential value?
Options
- APenalty
- BCost
- CRisk
- DDependency
How the community answered
(62 responses)- A5% (3)
- B2% (1)
- C92% (57)
- D2% (1)
Explanation
Risk: the chance that the requirement cannot deliver the potential value, or cannot be met at all. This may include many factors such as the difficulty of implementing a requirement, or the chance that stakeholders will not accept a solution component.
Topics