ECBA · Question #82
The requirements life cycle ends when:
The correct answer is A. solution and the requirements that represent it are retired. The requirements life cycle: - begins with the representation of a business need as a requirement, - continues through the development of a solution, and - ends when a solution and the requirements that represent it are retired.
Requirements Life Cycle Management
Question
The requirements life cycle ends when:
Options
- Asolution and the requirements that represent it are retired.
- Ball requirements are verified and validated by the stakeholders.
- Csolution is implemented and the project team disbands.
- Dsolution is defined and approved by the stakeholders.
How the community answered
(40 responses)- A95% (38)
- B3% (1)
- D3% (1)
Explanation
The requirements life cycle: - begins with the representation of a business need as a requirement, - continues through the development of a solution, and - ends when a solution and the requirements that represent it are retired.
Topics
#requirements lifecycle#solution retirement#lifecycle management