nerdexam
IIBA

ECBA · Question #82

The requirements life cycle ends when:

The correct answer is A. solution and the requirements that represent it are retired. The requirements life cycle: - begins with the representation of a business need as a requirement, - continues through the development of a solution, and - ends when a solution and the requirements that represent it are retired.

Requirements Life Cycle Management

Question

The requirements life cycle ends when:

Options

  • Asolution and the requirements that represent it are retired.
  • Ball requirements are verified and validated by the stakeholders.
  • Csolution is implemented and the project team disbands.
  • Dsolution is defined and approved by the stakeholders.

How the community answered

(40 responses)
  • A
    95% (38)
  • B
    3% (1)
  • D
    3% (1)

Explanation

The requirements life cycle: - begins with the representation of a business need as a requirement, - continues through the development of a solution, and - ends when a solution and the requirements that represent it are retired.

Topics

#requirements lifecycle#solution retirement#lifecycle management

Community Discussion

No community discussion yet for this question.

Full ECBA Practice