ECBA · Question #213

Which of the following tasks is used to ensure that requirements and designs at different levels are aligned to one another?

The correct answer is B. Trace requirements. The task Trace Requirements ensures that requirements and designs across different levels (business, stakeholder, solution) are consistently aligned with one another. This alignment supports scope management, impact analysis, verification and validation efforts, and change…

Requirements Life Cycle Management

Question

Which of the following tasks is used to ensure that requirements and designs at different levels are aligned to one another?

Options

  • AVerify requirements
  • BTrace requirements
  • CGather requirements
  • DAnalyze requirements

How the community answered

(56 responses)
  • A
    7% (4)
  • B
    89% (50)
  • C
    2% (1)
  • D
    2% (1)

Explanation

The task Trace Requirements ensures that requirements and designs across different levels (business, stakeholder, solution) are consistently aligned with one another. This alignment supports scope management, impact analysis, verification and validation efforts, and change Requirement tracing also: Clarifies relationships between business needs and solution features. Enables efficient scope monitoring and helps avoid scope creep. Supports linking requirements to their source and derived components.

Topics

#trace requirements#requirements alignment#requirements levels#traceability