In prioritizing requirements, which of the following factors include difficulty of implementing a requirement, or the likelihood that a requirement cannot deliver its potential value?
The correct answer is D. Risk. In the context of prioritizing requirements, risk refers to the difficulty of implementing a requirement or the likelihood that it cannot deliver its potential value. Risk-based prioritization considers uncertainties related to implementation, cost overruns, time delays, or…
Question
In prioritizing requirements, which of the following factors include difficulty of implementing a requirement, or the likelihood that a requirement cannot deliver its potential value?
Options
- ACost
- BDependency
- CPenalty
- DRisk
How the community answered
(67 responses)- A6% (4)
- B3% (2)
- C1% (1)
- D90% (60)
Explanation
In the context of prioritizing requirements, risk refers to the difficulty of implementing a requirement or the likelihood that it cannot deliver its potential value. Risk-based prioritization considers uncertainties related to implementation, cost overruns, time delays, or failure to achieve desired outcomes. High-risk requirements may be prioritized lower unless mitigated effectively.