IIBA
ECBA · Question #136
The process of assigning requirements to solution components and releases to best achieve the objectives is called:
The correct answer is C. requirements allocation. Requirements allocation is the process of assigning requirements to solution components and releases to best achieve the objectives.
Requirements Analysis and Design Definition
Question
The process of assigning requirements to solution components and releases to best achieve the objectives is called:
Options
- Arequirements classification schema.
- Brequirements traceability.
- Crequirements allocation.
- Drequirements architecture.
How the community answered
(36 responses)- A3% (1)
- B3% (1)
- C94% (34)
Explanation
Requirements allocation is the process of assigning requirements to solution components and releases to best achieve the objectives.
Topics
#requirements allocation#solution components#releases#requirements management
Community Discussion
No community discussion yet for this question.