Which of the following items is commonly used by a business analyst (BA) during requirements verification?
The correct answer is A. A checklist with a standard set of quality elements. Checklists may include a standard set of quality elements that business analysts use to verify the
Requirements Analysis and Design Definition
Question
Which of the following items is commonly used by a business analyst (BA) during requirements verification?
Options
- AA checklist with a standard set of quality elements
- BA business model canvas with financial estimates
- CA benchmarking report with industry comparisons
- DA user story with inputs and outputs
How the community answered
(19 responses)- A95% (18)
- C5% (1)
Explanation
Checklists may include a standard set of quality elements that business analysts use to verify the