Which stakeholder has responsibility to review and approve requirements?
The correct answer is A. Sponsor. Sponsor: responsible to review and approve the business case, solution or product scope, and all requirements and designs.
Business Analysis Key Concepts and Terminology
Question
Which stakeholder has responsibility to review and approve requirements?
Options
- ASponsor
- BBusiness analyst
- CProject manager
- DEnd user
How the community answered
(37 responses)- A86% (32)
- B3% (1)
- C3% (1)
- D8% (3)
Explanation
Sponsor: responsible to review and approve the business case, solution or product scope, and all requirements and designs.
Topics
#stakeholder roles#sponsor#requirements approval#sign-off authority