A customer needs a report which combines time wage types generated from time evaluation with employees' pay data from IT0008 (Basic Pay). What do you propose? Note: Please choose the correct answer.
The correct answer is C. Create an individual report based on the logical database PNPCE. See the full explanation below for the reasoning.
Question
A customer needs a report which combines time wage types generated from time evaluation with employees' pay data from IT0008 (Basic Pay). What do you propose? Note: Please choose the correct answer.
Options
- AUse standard report RPTABS20 (Absence and Attendance Data Overview)
- BUse standard report RPTBALOO (Cumulated Time Evaluation Results)
- CCreate an individual report based on the logical database PNPCE
- DCreate an individual cluster report
How the community answered
(26 responses)- A12% (3)
- B4% (1)
- C81% (21)
- D4% (1)