What are desired outcomes of an SAP BW/4HANA pilot project? Note: There are 3 correct answers to this question.
See the full explanation below for the reasoning.
Question
What are desired outcomes of an SAP BW/4HANA pilot project? Note: There are 3 correct answers to this question.
Options
- AConfirm increased database size using SAP BW/4HANA instead of a common RDBMS.
- BIdentify required changes for the business processes to comply with SAP BW/4HANA standard
- CIdentify customizing and configuration areas to be applied to future projects.
- DIdentify objects from SAP BI content and/or SAP HANA live that will be leveraged in subsequent
- ETransfer experience of the pilot project to future projects.
Community Discussion