The correct answer is A. Production LUN is in the process of rolling back after the test was completed. EMC E22-275 Exam
Question
Refer to the Exhibit. A customer has been testing emergency operations in case of a site failure. They notice that the Win_CG consistency group (CG) is out-of-sync between the production and disaster recovery sites. What happened to cause the consistency group to be out-of-sync?
Options
- AProduction LUN is in the process of rolling back after the test was completed
- BRPA cannot destage all data within the Required Protection Window
- CProduction LUN has failed to roll back and is now in Marking mode
- DCG is now in a Long Resync to destage changes from the production LUN
Explanation
EMC E22-275 Exam
Community Discussion