E22-275 Question #34: Real Exam Question with Answer & Explanation

The correct answer is A. Production LUN is in the process of rolling back after the test was completed. EMC E22-275 Exam

Question

Refer to the Exhibit. A customer has been testing emergency operations in case of a site failure. They notice that the Win_CG consistency group (CG) is out-of-sync between the production and disaster recovery sites. What happened to cause the consistency group to be out-of-sync?

Options

  • AProduction LUN is in the process of rolling back after the test was completed
  • BRPA cannot destage all data within the Required Protection Window
  • CProduction LUN has failed to roll back and is now in Marking mode
  • DCG is now in a Long Resync to destage changes from the production LUN

Explanation

EMC E22-275 Exam

Community Discussion

No community discussion yet for this question.