What is a key design consideration for a service provider to ensure that they can effectively process the termination of a service instance?

The correct answer is D. Automate the de-provisioning process to release resources. See the full explanation below for the reasoning.

Question

What is a key design consideration for a service provider to ensure that they can effectively process the termination of a service instance?

Options

  • AArchive the associated service data regardless of the user requirements
  • BIncorporate a retention period for private user data and user PCI data
  • CIncorporate a service grace period to prevent the actual deletion of the instance
  • DAutomate the de-provisioning process to release resources

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    13% (4)
  • D
    77% (24)

Community Discussion

No community discussion yet for this question.