E20-918 · Question #46

Refer to Scenario 5. EMC E20-918 Exam Your first goal in this proof-of-concept is to demonstrate one quick and successful backup run to the CSP for two different customer applications. Which two…

The correct answer is A. HR and Library. See the full explanation below for the reasoning.

Question

Refer to Scenario 5. EMC E20-918 Exam Your first goal in this proof-of-concept is to demonstrate one quick and successful backup run to the CSP for two different customer applications. Which two applications would you select if your desired outcome is backup completion within the shortest possible time?

Exhibit

E20-918 question #46 exhibit

Options

  • AHR and Library
  • BEmail and Library
  • CEmail and Legal
  • DLibrary and Legal

How the community answered

(17 responses)
  • A
    76% (13)
  • B
    12% (2)
  • C
    6% (1)
  • D
    6% (1)