An EMC customer has received a warning indicating that their Avamar server has crossed the 80% capacity threshold. Backups are completing within the backup window and there have been no recent…
The correct answer is A. Reassess retention policies. See the full explanation below for the reasoning.
Question
An EMC customer has received a warning indicating that their Avamar server has crossed the 80% capacity threshold. Backups are completing within the backup window and there have been no recent increases in the client change rates. Maintenance processes are running successfully and garbage collection is freeing up space at its expected rate. What is the best course of action to take at this time?
Options
- AReassess retention policies
- BSuspend backup activity
- CExtend the blackout window period by starting it earlier
- DActivate more clients to achieve higher deduplication rates
How the community answered
(40 responses)- A80% (32)
- B10% (4)
- C3% (1)
- D8% (3)